Update on the programme:
Monday 30 Jan - Walkways and Bridge 1 deck despatched from Wales. Arrive Afternoon at Robertsbridge.
Tuesday 31 January - Bridges 2 - 5 decks despatched from Lamberhurst and decks set on Northbridge Street carriageway, assemble walkways, take down cricket club fence and replace with temporary.
Wednesday 1 February - lay trackway and start bridge deck placing, Transport old bridge 2 deck to RBJS yard.
Thursday 2 February - complete bridge deck placing, complete bolting down of decks 2 - 5 and assemble bridge No 1 deck.
Friday 3 February - available if weather interrupts progress. Re-erect fencing to Playing and cricket fields.
We will need one or two volunteers from mid day Tuesday to direct traffic and prevent the general public from placing themselves in danger. Full PPE will be required and we will need to arrange some briefing sessions. Any response to the rota for 2 hour shifts from 8 a.m. to 6 p.m.
Monday 30 Jan - Walkways and Bridge 1 deck despatched from Wales. Arrive Afternoon at Robertsbridge.
Tuesday 31 January - Bridges 2 - 5 decks despatched from Lamberhurst and decks set on Northbridge Street carriageway, assemble walkways, take down cricket club fence and replace with temporary.
Wednesday 1 February - lay trackway and start bridge deck placing, Transport old bridge 2 deck to RBJS yard.
Thursday 2 February - complete bridge deck placing, complete bolting down of decks 2 - 5 and assemble bridge No 1 deck.
Friday 3 February - available if weather interrupts progress. Re-erect fencing to Playing and cricket fields.
We will need one or two volunteers from mid day Tuesday to direct traffic and prevent the general public from placing themselves in danger. Full PPE will be required and we will need to arrange some briefing sessions. Any response to the rota for 2 hour shifts from 8 a.m. to 6 p.m.